Power Totals
How much power Nevada's data centers say they need, stacked up against how much the tracked energy projects would actually generate: filterable by status and project type.
Filter by status
Filter by energy project type
Data center demand
9,455.45 MW
29 sites in filter · 6 without a reported figure
Energy project generation
21,575.4 MW
Solar, geothermal, gas & battery storage combined
Substation capacity
1,060 MVA
Transmission/transformer capacity, not generation
Battery storage capacity
29,055 MWh
Total energy stored, not a discharge rate (MW)
Demand vs. generation, at a glance
Data centers9,455.45 MW
Energy projects (generation)21,575.4 MW
Energy project generation by type
Substation6 projects786 MW
Solar34 projects13,476.2 MW
Geothermal29 projects652.5 MW
Gas12 projects6,278.7 MW
Pipeline3 projects0 MW
Battery Storage5 projects230 MW
Wind1 project152 MW
| Type | Projects | Generation (MW) | Substation (MVA) | Storage (MWh) | Missing data |
|---|---|---|---|---|---|
| Substation | 6 | 786 | 560 | — | 3 |
| Solar | 34 | 13,476.2 | 500 | 23,775 | 5 |
| Geothermal | 29 | 652.5 | — | — | 15 |
| Gas | 12 | 6,278.7 | — | — | 3 |
| Pipeline | 3 | — | — | — | 3 |
| Battery Storage | 5 | 230 | — | 5,280 | 2 |
| Wind | 1 | 152 | — | — | — |
| Total (90) | 90 | 21,575.4 | 1,060 | 29,055 |
Data centers by status
| Status | Sites | Demand (MW) | Missing data |
|---|---|---|---|
| Proposed | 4 | 1,000 | 3 |
| Approved | 7 | 5,625 | 1 |
| Under Construction | 12 | 1,542 | 2 |
| Operational | 6 | 1,288.45 | — |
| Cancelled | 0 | — | — |
| Total (29) | 29 | 9,455.45 |